The Northern Pipeline Interconnector (NPI) - Stage 1 is one of three major infrastructure projects delivered by the Southern Regional Water Pipeline Alliance (SRWPA) for LinkWater Projects, the state government's special purpose vehicle for the design and construction of water infrastructure. Its gazetted completion date was 31 December 2008 with final reinstatement of land now complete. This mostly underground pipeline spans 47km from Landers Shute to Morayfield. Please click here to view the NPI - Stage 1 map. The NPI - Stage 1 is part of the $9 billion South East Queensland (SEQ) Water Grid. The team was assembled in August 2006 with the first pipe laid in November 2007.
The SRWPA partners were KBR, Abigroup and McConnell Dowell, and LinkWater Projects as owner-participant. Project Statistics
*Prior to change in council boundaries in 2008 |